The school engaged a leading design/build performance contractor, with PremiStar as its mechanical contractor. Zach Glover, PremiStar’s VP of Construction, collaborated with the school facilities manager and performance contractor on each stage of the project, from assessment and system design to equipment selection, permitting, scheduling, installation, testing, and commissioning.
To accomplish its objectives, the facilities operations team approved the following upgrades to HVAC infrastructure:
• Rooftop HVAC Units: Installation of 39 ultra-high efficiency rooftop units using A2L refrigerant, ranging from 3 to 20 tons.
• Ductwork: Replacement of existing ductwork to boost energy efficiency and indoor air quality.
• VAV: Installation of 47 variable air volume (VAV) units for the regulation of individual classroom temperatures.
• Piping: Replacement of gas piping to enhance safety, efficiency, regulatory compliance, and cost savings.
• Air Filtration: Deployment of MERV 13 air filtration units to capture airborne particles, improving air quality and protecting HVAC components.
• Controls: Installation of building automation controls to maximize efficiency and reduce operating costs.